A building might contain:
200 socket outlets
300 luminaires
electric water heaters
air-conditioning equipment
kitchen appliances
EV chargers
lifts
pumps
ventilation equipment
server equipment.
Add the full rated load of everything together and the result can be enormous.
But will every item operate at full load at exactly the same time?
Usually not.
This is where maximum demand and diversity become an important part of electrical design.
They help the designer establish a realistic electrical demand for an installation without simply sizing every piece of upstream infrastructure for the theoretical sum of every connected load.
BS 7671 requires designers to determine the maximum demand of an installation or part of an installation and permits diversity to be considered when making that assessment. The IET also makes clear that maximum demand is ultimately an engineering-design responsibility rather than simply a figure supplied by the electricity network operator. IET Wiring Regulations
So how do we actually approach it?
What is connected load?
Let's start with the simplest term.
Connected load is essentially the electrical load represented by the equipment connected to the installation.
Imagine a small office contains:
10 × 150 W workstation loads
1 × 3 kW water heater
1 × 2 kW dishwasher
500 W of lighting
2 × 1 kW miscellaneous loads
The theoretical connected load would be:
1.5 + 3 + 2 + 0.5 + 2 = 9 kW
That's useful information.
But it doesn't necessarily mean the building will continuously draw 9 kW.
The water heater cycles.
The dishwasher only operates periodically.
Not every socket outlet is necessarily loaded.
The office might be empty overnight.
So we need to consider how those loads are actually used.
What is maximum demand?
Maximum demand is the highest electrical demand that the designer reasonably expects the installation — or a particular part of it — to require under normal operating conditions.
It is not necessarily the same as simply adding every connected load together.
The IET describes maximum demand as being established from the connected loads while considering appropriate diversity, but also stresses that the way maximum demand is assessed depends on what part of an installation is being designed. IET Wiring Regulations
For example, we might assess maximum demand at:
Final circuit level
↓
Distribution board
↓
Sub-main
↓
Main LV switchboard
↓
Incoming electrical supply
And the treatment of diversity may be different at each level.
That's an important concept.
What is electrical diversity?
Diversity recognises that electrical loads are unlikely to all reach their maximum demand simultaneously.
Consider an office kitchen containing:
kettle
microwave
dishwasher
water heater
fridge.
All five appliances are electrically connected.
But their operating patterns are different.
The fridge cycles automatically.
The dishwasher operates periodically.
The kettle operates for a few minutes.
The microwave may operate for only a couple of minutes.
That means the maximum simultaneous demand may be lower than the sum of every appliance's rated load.
This isn't an excuse to arbitrarily reduce loads.
It is an engineering assessment of how the installation is realistically expected to operate.
Maximum demand is not just “connected load × 60%”
This is probably one of the biggest misconceptions around diversity.
There is no universal rule that says:
Residential = X% diversity
Commercial = Y% diversity
The IET specifically warns against treating diversity this way. The appropriate assessment depends on the connected loads and how those loads are expected to operate. IET Wiring Regulations
Two buildings of exactly the same size can have completely different demand profiles.
Consider:
Building A:
Standard office operating 08:00–17:00.
Building B:
24-hour technology facility with significant cooling and server infrastructure.
They could have identical floor areas.
Their electrical demand could be completely different.
That is why diversity requires engineering judgement.
Diversity changes throughout the electrical system
This is easier to understand if we look at the electrical distribution hierarchy.
Imagine a commercial building containing ten distribution boards.
Each DB supplies twenty final circuits.
At final-circuit level, the designer might need to consider the actual maximum current that individual circuit can experience.
Move upstream to the distribution board and not every final circuit is likely to be fully loaded simultaneously.
Move further upstream to the main switchboard and the probability of every distribution board simultaneously reaching its individual peak may reduce again.
The IET describes this distinction when discussing diversity at final-circuit, distribution-board and whole-site levels. IET Wiring Regulations
In simple terms:
The further upstream we move, the more important understanding simultaneous demand becomes.
But that doesn't mean we simply keep reducing numbers.
We need to understand the loads.
Step 1 — Create a load schedule
The first practical step is identifying the electrical loads.
A commercial load schedule might look something like this:
LoadQuantityConnected LoadLighting—8 kWSmall power—25 kWMechanical plant—35 kWWater heating—12 kWKitchen equipment—20 kWLift115 kWEV charging—44 kWServer/ICT equipment—10 kW
The theoretical connected load is therefore:
169 kW
But that isn't automatically our maximum demand.
Now we need to investigate how each load operates.
Step 2 — Separate continuous and intermittent loads
One useful way to begin thinking about diversity is to classify the loads.
Loads that may operate for long periods
Examples could include:
server equipment
certain lighting loads
refrigeration
ventilation
process loads.
Intermittent loads
Examples might include:
water heaters
kitchen appliances
hand dryers
certain pumps
cleaners' equipment.
Controlled loads
Increasingly, buildings also contain loads whose demand can be actively managed.
For example:
EV chargers
battery systems
electric heating
smart building systems.
Understanding the operating profile is often more useful than simply looking at the nameplate rating.
Step 3 — Understand the building
This is where electrical design becomes more than mathematics.
Ask the client questions.
How many people will occupy the building?
What are the operating hours?
Will the kitchen be used continuously or only at lunchtime?
Are EV chargers available to everyone simultaneously?
Does mechanical equipment operate together or in duty/standby arrangements?
Is any equipment expected to run continuously?
Does the client expect future expansion?
The answers can materially change the electrical design.
A good load assessment should reflect the actual building.
Step 4 — Apply diversity appropriately
Once the operating characteristics are understood, the designer can assess the likely simultaneous demand.
Let's use a simplified example.
Suppose a distribution board contains:
Lighting: 8 kW
General small power: 20 kW
Water heating: 6 kW
Kitchen equipment: 8 kW
Dedicated ICT: 5 kW
Total connected load:
47 kW
The designer might determine from the equipment characteristics, client requirements and applicable guidance that the realistic simultaneous demand is lower than 47 kW.
The exact figure needs to be justified.
That's important.
Diversity should be based on information and engineering judgement — not simply chosen because it produces a convenient cable size.
What guidance exists for diversity?
BS 7671 establishes the requirement to assess maximum demand, but does not prescribe one universal set of diversity percentages for every installation.
The IET provides additional guidance through publications including its On-Site Guide, Electrical Installation Design Guide and other design guidance. The updated On-Site Guide now aligns with BS 7671:2018+A4:2026. IET Wiring Regulations
However, published diversity guidance should still be applied intelligently.
The IET notes that simplified guidance tends to err on the cautious side and that competent designers can use engineering judgement based on actual loads and operating profiles. IET Wiring Regulations
That distinction matters.
A table is guidance.
It doesn't understand the building.
The designer does.
Step 5 — Convert electrical power into current
Eventually, the designer needs an electrical current.
For a simplified single-phase resistive load:
I = P ÷ V
Where:
I = current in amperes
P = power in watts
V = voltage
For example, a 6.9 kW single-phase load at 230 V:
6,900 ÷ 230 = 30 A
For three-phase systems, the calculation also considers line voltage and power factor:
I = P ÷ (√3 × V × PF)
For example, if we had a balanced three-phase load of:
100 kW
at:
400 V
with a power factor of:
0.9
then:
100,000 ÷ (1.732 × 400 × 0.9)
≈ 160 A
Real electrical-design calculations may need to consider additional characteristics depending on the equipment.
Manufacturer information should always be used where available rather than assuming an arbitrary power factor. The IET specifically recommends using equipment data where possible. IET Wiring Regulations
Step 6 — Build the demand upstream
Now we can begin constructing the building load.
Imagine:
DB-GF-P01
Calculated maximum demand:
60 A
DB-GF-L01
Calculated maximum demand:
25 A
DB-FF-P01
Calculated maximum demand:
55 A
DB-FF-L01
Calculated maximum demand:
22 A
That does not necessarily mean the upstream switchboard must simply be designed around:
60 + 25 + 55 + 22 = 162 A
Why?
Because the maximum demand of each board may occur at different times.
For example:
Lighting demand may peak during dark winter afternoons.
Kitchen demand may peak around lunch.
Cleaners' power may peak after normal working hours.
EV charging may peak later in the day.
Understanding that coincidence is part of determining the upstream maximum demand.
What is coincidence?
This introduces another useful concept.
Coincidence asks:
How likely are separate electrical loads to reach their maximum demand at the same time?
Suppose ten apartments each have an individual maximum demand of 50 A.
That does not necessarily mean the incoming supply needs to provide:
10 × 50 = 500 A
because it may be highly unlikely that every apartment reaches 50 A simultaneously.
This becomes particularly important when designing:
apartment developments
hotels
student accommodation
offices
mixed-use developments
large commercial sites.
As projects become larger, historical load information and actual usage profiles can become increasingly valuable.
Existing buildings: measure the demand
When adding substantial new electrical loads to an existing installation, guessing can be unnecessary.
You may be able to measure it.
The IET recommends power logging as a useful method of verifying existing demand before significant new loads are added. IET Wiring Regulations
For example, suppose a client wants to install:
8 × 22 kW EV chargers
into an existing commercial building.
Looking at the main switch rating alone doesn't tell you how much spare capacity exists.
A suitable load survey could establish how the building actually operates over time.
The designer can then assess:
existing maximum demand
proposed additional demand
against:
available supply capacity
This is much stronger than assuming spare capacity based purely on the switchgear nameplate.
EV charging changes the conversation
EV charging has made maximum-demand assessment particularly important.
Imagine:
20 chargers × 22 kW
The theoretical connected load is:
440 kW
That could dramatically change the required incoming supply.
But modern EV infrastructure may use load management or load curtailment to control the combined charging demand.
Instead of allowing every charger to draw full power simultaneously, the system can dynamically distribute available capacity.
The IET notes that intelligent charging systems can be used to modulate overall EV demand, although the design still needs to consider the available supply and how the control system operates. IET Wiring Regulations
This is becoming an increasingly important skill for electrical designers.
Heat pumps, electric heating and electrification
EVs aren't the only reason maximum demand is becoming more important.
Buildings are becoming increasingly electrified.
We're replacing fossil-fuel systems with:
heat pumps
electric water heating
EV charging
battery storage
electrically driven building systems.
That means electrical designers are increasingly dealing with larger loads.
A building which historically required a modest electrical supply can now require substantial additional capacity.
The load assessment therefore needs to begin early in the design process.
Finding out during construction that the building requires a larger utility connection can have serious cost and programme consequences.
Don't forget future capacity
Suppose your calculated maximum demand is:
180 A
Would you automatically specify equipment rated exactly at 180 A?
Probably not.
The project might require allowance for:
tenant changes
additional equipment
EV charging
future expansion
replacement plant
spare ways.
The IET notes that it can be sensible to provide additional capacity in distribution circuits so future loads can be accommodated, provided the cable and protective-device relationship remains correctly designed. IET Wiring Regulations
There is a balance.
Oversizing everything wastes money.
Designing everything with zero spare capacity can create problems later.
Good electrical design sits somewhere between the two.
Maximum demand affects more than the incoming supply
Once established, maximum demand can influence:
Utility supply requirements
Is the existing service adequate?
Transformer sizing
Is a dedicated transformer required?
Main switchboard rating
What continuous current must the switchboard accommodate?
Sub-main cables
What design current needs to be carried?
Distribution boards
What rating should the DB have?
Standby generation
Which loads need supporting?
UPS systems
What critical demand exists?
Renewable-energy systems
How does generation interact with consumption?
Battery storage
What energy and power requirements actually exist?
Maximum demand sits near the beginning of many electrical-design decisions.
Maximum demand versus design current
These terms are related, but they shouldn't be casually treated as interchangeable in every situation.
At an individual circuit level, the designer needs to establish the design current, usually represented as:
Ib
The circuit is then designed so that the protective device and conductor satisfy the relevant relationships required by BS 7671.
A familiar fundamental relationship is:
Ib ≤ In ≤ Iz
Where:
Ib = design current
In = protective-device rated current
Iz = conductor current-carrying capacity
The IET emphasises this relationship when discussing protective-device and cable selection. IET Wiring Regulations
Maximum demand may help determine Ib, particularly for distribution circuits.
But we still need to complete the rest of the circuit design.
Common maximum-demand mistakes
1. Adding every protective device rating together
A DB containing:
10 × 32 A breakers
does not automatically have a maximum demand of:
320 A
Breaker ratings are not the same thing as actual connected load.
2. Applying one diversity percentage to everything
“It's commercial, so use 80%.”
That's not a proper load assessment.
Different loads have different operating characteristics.
3. Applying diversity twice
This is easy to do in large spreadsheets.
A designer may apply diversity to individual DBs and then unintentionally apply another aggressive factor upstream without considering whether the first calculation already reflected coincidence.
Check the methodology carefully.
4. Ignoring equipment duty
A 15 kW motor that runs continuously is very different from a 15 kW appliance that operates for five minutes each day.
Same rating.
Very different load profile.
5. Assuming existing spare capacity
An existing 400 A switchboard does not automatically mean there is 400 A available for a new load.
Find out what is already being used.
6. Ignoring future loads
Designing right to the limit can make relatively small future alterations expensive.
7. Using guessed power factors
Where equipment information exists, use it.
Manufacturer data is preferable to assumptions. IET Wiring Regulations
A practical maximum-demand workflow
A useful electrical-design process is:
1. Identify every significant load
Create the connected load schedule.
↓
2. Confirm equipment information
Obtain manufacturer data where possible.
↓
3. Understand building operation
Occupancy, operating hours, duty cycles and client requirements.
↓
4. Categorise the loads
Continuous, intermittent, controlled, standby and so on.
↓
5. Assess diversity
Using appropriate guidance, operating profiles and engineering judgement.
↓
6. Calculate demand at DB level
Establish the demand of individual distribution boards.
↓
7. Build the load upstream
Assess sub-mains and main distribution.
↓
8. Consider coincidence
Determine which loads are realistically simultaneous.
↓
9. Compare against the available supply
Confirm whether the electrical infrastructure is adequate.
↓
10. Add appropriate future capacity
Consider realistic expansion requirements.
↓
11. Coordinate the design
Update:
schematics
load schedules
distribution-board schedules
cable calculations
utility applications.
↓
12. QA the assessment
Check formulas, assumptions and input data before issue.
Example maximum-demand calculation
Let's look at a simplified office.
Connected loads
ServiceConnected LoadLighting12 kWSmall power35 kWMechanical plant42 kWHot water12 kWLift15 kWICT10 kWEV charging44 kW Total 170 kW
Our theoretical connected load is therefore:
170 kW
The designer now investigates the operation of each system.
They determine that:
some equipment is intermittent
certain mechanical plant does not operate simultaneously
the EV chargers use managed charging
ICT operates continuously
the lighting demand is relatively predictable
the client's occupancy profile is known.
Following an appropriate engineering assessment, the designer establishes a lower maximum simultaneous demand.
That figure — not simply the 170 kW connected load — then becomes part of the upstream electrical design.
The key point is that the reduction must be defensible.
Someone reviewing the calculation should be able to understand:
where the loads came from
and
why the diversity was applied.
Your load assessment should tell a story
A good load schedule shouldn't just contain numbers.
It should show how the design was developed.
For example:
Architecture
tells us what spaces exist.
↓
Mechanical schedule
tells us plant loads.
↓
Small power design
provides equipment and socket demand.
↓
Lighting design
provides lighting loads.
↓
Specialist systems
add further loads.
↓
Load assessment
combines them.
↓
Maximum demand
determines the infrastructure.
↓
Single-line diagram
shows how that infrastructure is distributed.
That is why electrical documents need to remain coordinated.
A change in one place can affect several others.
Maximum demand is an engineering decision
The biggest lesson is this:
Maximum demand isn't simply a formula.
Calculations are part of it.
But so are:
client discussions
manufacturer information
operating profiles
historical measurements
design guidance
professional judgement.
The IET itself recognises that experienced designers may use engineering judgement based on real loads and usage rather than treating simplified diversity guidance as an absolute rule. IET Wiring Regulations
That is an important distinction between simply completing a spreadsheet and actually designing an electrical installation.
Final thoughts
Maximum demand connects the building to the electrical infrastructure serving it.
Get it substantially wrong in one direction and the project may pay for oversized:
supplies
switchgear
cables
transformers.
Get it substantially wrong in the other direction and the installation may not have enough electrical capacity.
The aim is therefore not to produce the smallest number possible.
And it isn't to produce the largest number possible.
It's to produce the most realistic, technically justified design demand possible.
Once you've established that figure, you can begin answering the next question:
What size cable is required to carry it?
And that's exactly where we'll go next.